45-minute pre-mortem: set the failure scenario, collect reasons silently, share, cluster and prioritise, agree countermeasures and owners.
“Imagine it's a year from now and the project has failed badly.” Explain: the goal is to find risks, not blame.
Everyone writes as many reasons for the failure as possible – one reason per sticky note.
Sticky notes, pens
Each person reads one reason at a time and places it on the board until all are shared. No discussion.
Board
Group similar reasons and dot-vote the top three risks.
Dot stickers
Three groups, one top risk each.
Each small group takes one of the top three risks: How do we prevent it? How do we spot it early? Who owns it?
Each group presents its countermeasures in one minute; others add to them.
Add risks and actions to the project document, set a review date.